Douie Solar — Project Summary

Queue ID
ERCOT-26INR0098
Capacity
221.2 MW
Technology
Solar
Status
active
Location
Freestone, TX
Region
ERCOT
Developer
Buffalo Spring Solar LLC
IA Status
Facility Study

Douie Solar

BetaActiveSolarERCOTLBNL + Live

221.2 MW generation in Freestone, TX · In queue since May 2023 · Proposed COD April 2028

221.2 MW

Capacity

1

Components

Solar

2y 10m

In Queue

Facility Study

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

4y 11m

Facilities Study50%
Queue EntryMay 15, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-04-18

Project Details

State

TX

County

Freestone

Region

ERCOT

Developer

Buffalo Spring Solar LLC

Utility

Entity

ERCOT

Point of Interconnection

Tap 138 kV 3501 Sea way Teague - 3394 Jewett

Data Source

LBNL + Live

No news available for this project.