La Salle ESS
BetaActiveBatteryERCOTLBNL + Live
503.9 MW storage in La Salle, TX · In queue since April 2023 · Proposed COD February 2028
503.9 MW
Capacity
1
Components
Battery
2y 11m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
4y 10m
Facilities Study50%
Queue EntryApr 7, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-02-12
Project Details
State
TX
County
La Salle
Region
ERCOT
Developer
OCI La Salle ESS LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 345kV LOBO7A (#80219) - FOWLERTONSW5 (#5709) CKT#2
Data Source
LBNL + Live