La Salle Solar — Project Summary

Queue ID
ERCOT-26INR0088
Capacity
503.9 MW
Technology
Solar
Status
active
Location
La Salle, TX
Region
ERCOT
Developer
OCI La Salle Solar LLC
IA Status
Facility Study

La Salle Solar

ERCOT-26INR0088BetaActiveSolarERCOTLBNL + Live

503.9 MW generation in La Salle, TX · In queue since April 2023 · Proposed COD July 2027

503.9 MW

Capacity

1

Components

Solar

3 years

In Queue

Facility Study

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

4y 3m

Facilities Study50%
Queue EntryApr 19, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-07-01

Project Details

State

TX

County

La Salle

Region

ERCOT

Developer

OCI La Salle Solar LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

Tap 345kV LOBO7A (#80219) - FOWLERTONSW5 (#5709)

Data Source

LBNL + Live

Linked EIA Plant

La Salle Solar

EIA Plant ID: 68354

View Plant
No news available for this project.