Matias Solar
BetaActiveSolarERCOTLBNL
152.3 MW generation in Matagorda, TX · In queue since March 2023 · Proposed COD March 2027
152.3 MW
Capacity
1
Components
Solar
3 years
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
4 years
Facilities Study50%
Queue EntryMar 13, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-03-31
Project Details
State
TX
County
Matagorda
Region
ERCOT
Developer
Industrial Bravo Project II LLC
Utility
—
Entity
ERCOT
Point of Interconnection
8114 Conoco 138kV
Data Source
LBNL
No news available for this project.