Charro Creek Solar 2 SLF
BetaActiveSolarERCOTLBNL + Live
203 MW generation in Karnes, TX · In queue since March 2023 · Proposed COD July 2026
203 MW
Capacity
1
Components
Solar
3 years
In Queue
Facility Study
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
3y 4m
Facilities Study50%
Queue EntryMar 8, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-07-01
Project Details
State
TX
County
Karnes
Region
ERCOT
Developer
Charro Creek Solar LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 345kV 5725 PAWNEESW5 - 8164 COLETO7A
Data Source
LBNL + Live