Paluxy Storage
BetaActiveBatteryERCOTLBNL
511.68 MW storage in Victoria, TX · In queue since January 2023 · Proposed COD June 2027
511.68 MW
Capacity
1
Components
Battery
3y 2m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
4y 5m
Facilities Study50%
Queue EntryJan 3, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-06-30
Project Details
State
TX
County
Victoria
Region
ERCOT
Developer
S&S Renewables LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Double tapping: 345kV 5915 STP - 5133 Elm Creek ckt#1 and 345kV 5068 Cachena _x0013_ 5323 Old Hickory ckt#2
Data Source
LBNL
No news available for this project.