Valhalla Solar
BetaActiveSolarERCOTLBNL
306.8 MW generation in Brazoria, TX · In queue since March 2023 · Proposed COD May 2026
306.8 MW
Capacity
1
Components
Solar
3 years
In Queue
IA Executed
IA Status
Signed Dec 2023
Interconnection Timeline
Queue → IA
9 months
IA → COD
2y 5m
Total Duration
9 months
Construction75%
Queue EntryMar 9, 2023
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementDec 6, 2023
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2026-05-31
Project Details
State
TX
County
Brazoria
Region
ERCOT
Developer
Industrial Papa Project LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 138 kV 42215 Copper to 42195 Booster
Data Source
LBNL
No news available for this project.