Bracero Pecan Storage
ERCOT-26INR0034BetaActiveBatteryERCOTLBNL + Live
232 MW storage in Reeves, TX · In queue since November 2022 · Proposed COD July 2027
232 MW
Capacity
1
Components
Battery
3y 5m
In Queue
IA Executed
IA Status
Signed Jun 2024
Interconnection Timeline
Queue → IA
1y 7m
IA → COD
3y 1m
Total Duration
1y 7m
Construction75%
Queue EntryNov 7, 2022
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementJun 27, 2024
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 6–18 months
Commercial Operation
Proposed COD: 2027-07-01
Project Details
State
TX
County
Reeves
Region
ERCOT
Developer
Bracero Pecan Storage LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
60716 SARAGOSA 138kV
Data Source
LBNL + Live