Fairway Storage
ERCOT-26INR0033BetaActiveBatteryERCOTLBNL + Live
121.03 MW storage in Freestone, TX · In queue since November 2022 · Proposed COD September 2027
121.03 MW
Capacity
1
Components
Battery
3y 5m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
4y 10m
Facilities Study50%
Queue EntryNov 7, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-09-24
Project Details
State
TX
County
Freestone
Region
ERCOT
Developer
Fairway Storage LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138kV 3503 FAIRWPOD_8 - 196 FAIRFIELD
Data Source
LBNL + Live
No news available for this project.