Perry Creek Solar SLF
BetaActiveSolarERCOTLBNL
102.04 MW generation in Freestone, TX · In queue since December 2022 · Proposed COD March 2027
102.04 MW
Capacity
1
Components
Solar
3y 3m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
4y 3m
Facilities Study50%
Queue EntryDec 7, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-03-24
Project Details
State
TX
County
Freestone
Region
ERCOT
Developer
Perry Creek Solar, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
345kV Navarro (#68091) to Limestone (# 46020)
Data Source
LBNL
No news available for this project.