HyFuels Calhoun Solar
BetaActiveSolarERCOTLBNL + Live
301.82 MW generation in Victoria, TX · In queue since October 2022 · Proposed COD October 2027
301.82 MW
Capacity
1
Components
Solar
3y 5m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
5 years
Facilities Study50%
Queue EntryOct 18, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-10-01
Project Details
State
TX
County
Victoria
Region
ERCOT
Developer
HyFuels Green Lake Solar LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 345kV 8715 RADIANT7A - 8728 COBRA7A
Data Source
LBNL + Live
No news available for this project.