Becerra Creek Storage 1 — Project Summary

Queue ID
ERCOT-26INR0024
Capacity
125.62 MW
Technology
Battery
Status
active
Location
Webb, TX
Region
ERCOT
Developer
Bordas Renewable Energy, LLC
IA Status
Facility Study

Becerra Creek Storage 1

BetaActiveBatteryERCOTLBNL + Live

125.62 MW storage in Webb, TX · In queue since September 2022 · Proposed COD December 2027

125.62 MW

Capacity

1

Components

Battery

3y 6m

In Queue

Facility Study

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

5y 3m

Facilities Study50%
Queue EntrySep 21, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-12-01

Project Details

State

TX

County

Webb

Region

ERCOT

Developer

Bordas Renewable Energy, LLC

Utility

Entity

ERCOT

Point of Interconnection

345 kV Cenizo Substation (#80220)

Data Source

LBNL + Live

No news available for this project.