Leon Solar Park
210.1 MW generation in Leon, TX · In queue since September 2022 · Proposed COD July 2026
210.1 MW
Capacity
1
Components
Solar
3y 7m
In Queue
IA Executed
IA Status
Signed May 2024
Queue → IA
1y 8m
IA → COD
2y 2m
Total Duration
1y 8m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2026-07-01
State
TX
County
Leon
Region
ERCOT
Developer
Misae Solar IV LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138kV Grapeland Magnolia Tap (bus #3355) to Pleasant Springs POI (bus# 3357) section of the Jewett -Crockett 138kV Line
Data Source
LBNL + Live