Leon Solar Park — Project Summary

Queue ID
ERCOT-26INR0023
Capacity
210.1 MW
Technology
Solar
Status
active
Location
Leon, TX
Region
ERCOT
Developer
Misae Solar IV LLC
IA Status
IA Executed

Leon Solar Park

ERCOT-26INR0023BetaActiveSolarERCOTLBNL + Live

210.1 MW generation in Leon, TX · In queue since September 2022 · Proposed COD July 2026

210.1 MW

Capacity

1

Components

Solar

3y 7m

In Queue

IA Executed

IA Status

Signed May 2024

Interconnection Timeline

Queue → IA

1y 8m

IA → COD

2y 2m

Total Duration

1y 8m

Construction75%
Queue EntrySep 15, 2022

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementMay 21, 2024

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2026-07-01

Project Details

State

TX

County

Leon

Region

ERCOT

Developer

Misae Solar IV LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

Tap 138kV Grapeland Magnolia Tap (bus #3355) to Pleasant Springs POI (bus# 3357) section of the Jewett -Crockett 138kV Line

Data Source

LBNL + Live

No news available for this project.