Crossroads Wind
ERCOT-26INR0021BetaActiveWindERCOTLBNL + Live
253.29 MW generation in Victoria, TX · In queue since September 2022 · Proposed COD June 2027
253.29 MW
Capacity
1
Components
Wind
3y 7m
In Queue
IA Executed
IA Status
Signed Jul 2024
Interconnection Timeline
Queue → IA
1y 10m
IA → COD
2y 11m
Total Duration
1y 10m
Construction75%
Queue EntrySep 27, 2022
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementJul 24, 2024
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–36 months
Commercial Operation
Proposed COD: 2027-06-30
Project Details
State
TX
County
Victoria
Region
ERCOT
Developer
HyFuels Green Lake Wind LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138 KV 8723 Cangrejo - 8721 BEECHER
Data Source
LBNL + Live