Puerto Del Sol 1 — Project Summary

Queue ID
ERCOT-26INR0008
Capacity
213.8 MW
Technology
Solar
Status
active
Location
Cameron, TX
Region
ERCOT
Developer
PUERTO DEL SOL, LLC
IA Status
Facility Study

Puerto Del Sol 1

BetaActiveSolarERCOTLBNL + Live

213.8 MW generation in Cameron, TX · In queue since May 2022 · Proposed COD December 2026

213.8 MW

Capacity

1

Components

Solar

3y 10m

In Queue

Facility Study

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

4y 7m

Facilities Study50%
Queue EntryMay 16, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-12-31

Project Details

State

TX

County

Cameron

Region

ERCOT

Developer

PUERTO DEL SOL, LLC

Utility

Entity

ERCOT

Point of Interconnection

Tap 345kV 79500 Palmito - 79501 King Fisher Ckt 1

Data Source

LBNL + Live