Poteet BESS
BetaActiveBatteryERCOTLBNL
9.95 MW storage in Atascosa, TX · In queue since October 2024 · Proposed COD April 2025
9.95 MW
Capacity
1
Components
Battery
1y 5m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
6 months
Schedule
12 months past proposed COD
In Study38%
Queue EntryOct 17, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-04-01
Project Details
State
TX
County
Atascosa
Region
ERCOT
Developer
HEN INFRASTRUCTURE, LLC 1
Utility
—
Entity
ERCOT
Point of Interconnection
TSP Station Name: POTEET SUB TSP Station Code: POTEETS Load Name: POTEE_1 Bus#: 5710 kV: 69
Data Source
LBNL