Abilene Elmcreek BESS
9.9 MW storage in Taylor, TX · In queue since September 2024 · Proposed COD June 2025
9.9 MW
Capacity
1
Components
Battery
1y 6m
In Queue
IA Executed
IA Status
Signed Aug 2024
IA → COD
10 months
Total Duration
1y 6m
Schedule
9 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2025-06-30
State
TX
County
Taylor
Region
ERCOT
Developer
DGSP2 LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Station Name: Abilene Elm Creek TSP Station Code: ELMCRK Load Transformer name: LOAD1 Bus#: 6255 Voltage in kV (Transmission Level): 138kV
Data Source
LBNL