Compton BESS — Project Summary

Queue ID
ERCOT-25INR0699
Capacity
9.95 MW
Technology
Battery
Status
active
Location
Dallas, TX
Region
ERCOT
Developer
SMT Dallas VII LLC
IA Status
In Progress (unknown study)

Compton BESS

BetaActiveBatteryERCOTLBNL

9.95 MW storage in Dallas, TX · In queue since August 2024 · Proposed COD May 2025

9.95 MW

Capacity

1

Components

Battery

1y 7m

In Queue

In Progress (unknown study)

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

9 months

Schedule

11 months past proposed COD

In Study38%
Queue EntryAug 29, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-05-15

Project Details

State

TX

County

Dallas

Region

ERCOT

Developer

SMT Dallas VII LLC

Utility

Entity

ERCOT

Point of Interconnection

POIB 2981 ERCOT Bus name COMPTON1_8 ERCOT load name LDLXFMR1 Oncor XFMR number 1

Data Source

LBNL

No news available for this project.