PHOTON SOLAR 4 SLF
BetaActiveSolarERCOTLBNL + Live
105.98 MW generation in Wharton, TX · In queue since September 2024 · Proposed COD February 2026
105.98 MW
Capacity
1
Components
Solar
1y 6m
In Queue
Facility Study
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
1y 5m
Schedule
1 months past proposed COD
Facilities Study50%
Queue EntrySep 4, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-02-16
Project Details
State
TX
County
Wharton
Region
ERCOT
Developer
GulfStar Power, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
44880 Waterh_POI_5 345kV
Data Source
LBNL + Live