Fagus Solar Park 2 SLF
166.57 MW generation in Childress, TX · In queue since June 2024 · Proposed COD March 2026
166.57 MW
Capacity
1
Components
Solar
1y 10m
In Queue
IA Executed
IA Status
Signed Feb 2019
IA → COD
7y 1m
Total Duration
1y 10m
Schedule
1 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2026-03-15
State
TX
County
Childress
Region
ERCOT
Developer
Excel Advantage Services, LLC dba Misae Solar Park II
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
60501 Tesla 345 kV
Data Source
LBNL + Live