GIBSON BRANCH BESS
BetaActiveBatteryERCOTLBNL + Live
142.9 MW storage in Lampasas, TX · In queue since May 2024 · Proposed COD January 2028
142.9 MW
Capacity
1
Components
Battery
1y 10m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
3y 8m
Facilities Study50%
Queue EntryMay 20, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-01-15
Project Details
State
TX
County
Lampasas
Region
ERCOT
Developer
Gibson Branch BESS LLC
Utility
—
Entity
ERCOT
Point of Interconnection
7064 Lampasas Substation 138kV
Data Source
LBNL + Live
No news available for this project.