McCrae Energy Storage
ERCOT-25INR0661BetaActiveBatteryERCOTLBNL + Live
306.35 MW storage in Erath, TX · In queue since May 2024 · Proposed COD September 2028
306.35 MW
Capacity
1
Components
Battery
1y 11m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
4y 4m
Facilities Study50%
Queue EntryMay 20, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-09-25
Project Details
State
TX
County
Erath
Region
ERCOT
Developer
McCrae Energy Storage, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345 kV 1900 COMCHPKW_5 - 1440 COMCHESS1_5
Data Source
LBNL + Live