Jenna Eco-Electric Solar
BetaActiveSolarERCOTLBNL + Live
576.3 MW generation in Fisher, TX · In queue since May 2024 · Proposed COD April 2028
576.3 MW
Capacity
1
Components
Solar
1y 10m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
3y 11m
Facilities Study50%
Queue EntryMay 20, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-04-19
Project Details
State
TX
County
Fisher
Region
ERCOT
Developer
Clean Energy Holdings, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 345 kV 1048 Tonkawa Switch - 1430 Graham SES
Data Source
LBNL + Live
No news available for this project.