Carolina Storage Midland
BetaActiveBatteryERCOTLBNL + Live
203.6 MW storage in Howard, TX · In queue since July 2024 · Proposed COD October 2028
203.6 MW
Capacity
1
Components
Battery
1y 8m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
4y 3m
Facilities Study50%
Queue EntryJul 1, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-10-03
Project Details
State
TX
County
Howard
Region
ERCOT
Developer
CSE Storage, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 345kV 10057 Prong Moss Switch - 10062 Rockhound Switch CKT 1
Data Source
LBNL + Live
No news available for this project.