Carolina Storage Odessa
BetaActiveBatteryERCOTLBNL + Live
202.05 MW storage in Howard, TX · In queue since February 2024 · Proposed COD May 2029
202.05 MW
Capacity
1
Components
Battery
2y 1m
In Queue
Facility Study
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
5y 3m
Facilities Study50%
Queue EntryFeb 2, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-05-01
Project Details
State
TX
County
Howard
Region
ERCOT
Developer
CSE STORAGE, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
1058 LONGSHORE 345kV
Data Source
LBNL + Live