Carrizo Springs BESS
9.99 MW storage in Dimmit, TX · In queue since August 2024 · Proposed COD May 2025
9.99 MW
Capacity
1
Components
Battery
1y 7m
In Queue
IA Executed
IA Status
Signed Nov 2023
IA → COD
1y 6m
Total Duration
1y 7m
Schedule
10 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2025-05-30
State
TX
County
Dimmit
Region
ERCOT
Developer
Regis Carrizo Springs LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Station Name: CARRIZO SPRINGS Station Code: CARIZZO Load/Load XFMR Name: LOAD1 PTI Bus Number: #8244 Voltage in kV (Transmission): 69 kV Distribution Voltage: 12.47 kV
Data Source
LBNL