Zeus Armstrong Solar — Project Summary

Queue ID
ERCOT-25INR0586
Capacity
509.6 MW
Technology
Solar
Status
active
Location
Armstrong, TX
Region
ERCOT
Developer
Armstrong Solar, LLC
IA Status
Facility Study

Zeus Armstrong Solar

BetaActiveSolarERCOTLBNL + Live

509.6 MW generation in Armstrong, TX · In queue since May 2024 · Proposed COD April 2028

509.6 MW

Capacity

1

Components

Solar

1y 10m

In Queue

Facility Study

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

3y 11m

Facilities Study50%
Queue EntryMay 20, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-04-17

Project Details

State

TX

County

Armstrong

Region

ERCOT

Developer

Armstrong Solar, LLC

Utility

Entity

ERCOT

Point of Interconnection

Tap 345KV 23900 AlLIBATES -23914 TULECNYN

Data Source

LBNL + Live

No news available for this project.