CPS Energy AvR1CT2 Rotor Replacement
BetaActiveGasERCOTLBNL + Live
23.2 MW generation in Bexar, TX · In queue since October 2023 · Proposed COD March 2026
23.2 MW
Capacity
1
Components
Gas
2y 5m
In Queue
Facility Study
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
2y 5m
Facilities Study50%
Queue EntryOct 13, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-03-28
Project Details
State
TX
County
Bexar
Region
ERCOT
Developer
CPS Energy
Utility
—
Entity
ERCOT
Point of Interconnection
5475 Braunig 345kV
Data Source
LBNL + Live
No news available for this project.