Indigo Storage 3
BetaActiveBatteryERCOTLBNL + Live
60 MW storage in Fisher, TX · In queue since November 2023 · Proposed COD September 2027
60 MW
Capacity
1
Components
Battery
2y 4m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
3y 10m
Facilities Study50%
Queue EntryNov 14, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-09-17
Project Details
State
TX
County
Fisher
Region
ERCOT
Developer
Innovative Solar 245, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
tap 345 kV 68001 Claytonville _x0013_ 68004 Phantom Hill Circuit 2
Data Source
LBNL + Live
No news available for this project.