Silver Birch BESS
BetaActiveBatteryERCOTLBNL
208.8 MW storage in Brazos, TX · In queue since February 2024 · Proposed COD December 2026
208.8 MW
Capacity
1
Components
Battery
2y 1m
In Queue
Facility Study
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
2y 10m
Facilities Study50%
Queue EntryFeb 2, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-12-31
Project Details
State
TX
County
Brazos
Region
ERCOT
Developer
Silver Birch BESS, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 345 kV 3400 Twin Oak - 967 Gibbons Creek
Data Source
LBNL
No news available for this project.