Monument Hill Solar
ERCOT-25INR0512BetaActiveSolarERCOTLBNL + Live
200 MW generation in Fayette, TX · In queue since October 2023 · Proposed COD June 2029
200 MW
Capacity
1
Components
Solar
2y 6m
In Queue
Facility Study
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
5y 8m
Facilities Study50%
Queue EntryOct 13, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-06-30
Project Details
State
TX
County
Fayette
Region
ERCOT
Developer
RWE Solar Development, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV 7055 Fayette - 9074 Lytton Springs
Data Source
LBNL + Live
No news available for this project.