Lazy Frog Solar SLF
BetaActiveSolarERCOTLBNL + Live
105.8 MW generation in Franklin, TX · In queue since September 2023 · Proposed COD April 2028
105.8 MW
Capacity
1
Components
Solar
2y 6m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
4y 7m
Facilities Study50%
Queue EntrySep 22, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-04-17
Project Details
State
TX
County
Franklin
Region
ERCOT
Developer
Lazy Frog Solar, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
11688 Thorn Tree Switch 345kV
Data Source
LBNL + Live
No news available for this project.