Longday Solar SLF — Project Summary

Queue ID
ERCOT-25INR0501
Capacity
200.8 MW
Technology
Solar
Status
active
Location
Kinney, TX
Region
ERCOT
Developer
Longday Solar
IA Status
Facility Study

Longday Solar SLF

BetaActiveSolarERCOTLBNL + Live

200.8 MW generation in Kinney, TX · In queue since July 2023 · Proposed COD December 2027

200.8 MW

Capacity

1

Components

Solar

2y 8m

In Queue

Facility Study

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

4y 5m

Facilities Study50%
Queue EntryJul 31, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-12-15

Project Details

State

TX

County

Kinney

Region

ERCOT

Developer

Longday Solar

Utility

Entity

ERCOT

Point of Interconnection

Tap138 kV 8252 Brackettville - 8260 Escondido

Data Source

LBNL + Live