Longday Solar SLF
BetaActiveSolarERCOTLBNL + Live
200.8 MW generation in Kinney, TX · In queue since July 2023 · Proposed COD December 2027
200.8 MW
Capacity
1
Components
Solar
2y 8m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
4y 5m
Facilities Study50%
Queue EntryJul 31, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-12-15
Project Details
State
TX
County
Kinney
Region
ERCOT
Developer
Longday Solar
Utility
—
Entity
ERCOT
Point of Interconnection
Tap138 kV 8252 Brackettville - 8260 Escondido
Data Source
LBNL + Live
No news available for this project.