PHOTON SOLAR 1 2 SLF
ERCOT-25INR0493BetaActiveSolarERCOTLBNL + Live
235.66 MW generation in Wharton, TX · In queue since September 2024 · Proposed COD February 2026
235.66 MW
Capacity
1
Components
Solar
1y 7m
In Queue
IA Executed
IA Status
Signed Oct 2021
Interconnection Timeline
IA → COD
4y 4m
Total Duration
1y 7m
Schedule
2 months past proposed COD
Construction75%
Queue EntrySep 2, 2024
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementOct 1, 2021
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2026-02-16
Project Details
State
TX
County
Wharton
Region
ERCOT
Developer
GulfStar Power, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
44880 Waterh_POI_5 345kV
Data Source
LBNL + Live
No news available for this project.