Marick Rose BESS
BetaActiveBatteryERCOTLBNL + Live
50.18 MW storage in Fort Bend, TX · In queue since July 2023 · Proposed COD May 2026
50.18 MW
Capacity
1
Components
Battery
2y 8m
In Queue
Facility Study
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
2y 10m
Facilities Study50%
Queue EntryJul 10, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-05-01
Project Details
State
TX
County
Fort Bend
Region
ERCOT
Developer
Marick BESS
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 138kV 44521 Marick - 44615 Rosenberg Ckt 60
Data Source
LBNL + Live