Vault Solar
BetaActiveSolarERCOTLBNL + Live
108.5 MW generation in Palo Pinto, TX · In queue since June 2023 · Proposed COD December 2027
108.5 MW
Capacity
1
Components
Solar
2y 9m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
4y 6m
Facilities Study50%
Queue EntryJun 28, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-12-31
Project Details
State
TX
County
Palo Pinto
Region
ERCOT
Developer
PPM THR Solar
Utility
—
Entity
ERCOT
Point of Interconnection
Tap #331 Rwmiller - #320 Jaybird 138kV
Data Source
LBNL + Live