Bell Creek BESS
200.9 MW storage in Brazoria, TX · In queue since June 2023 · Proposed COD October 2027
200.9 MW
Capacity
1
Components
Battery
2y 10m
In Queue
IA Executed
IA Status
Signed Nov 2024
Queue → IA
1y 5m
IA → COD
2y 11m
Total Duration
1y 5m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2027-10-30
State
TX
County
Brazoria
Region
ERCOT
Developer
BELL CREEK BESS, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138kV 39500 West Colombia - 39703 FM524
Data Source
LBNL + Live
Linked EIA Plant
Bell Creek BESS LLC
EIA Plant ID: 67535