Tyler BESS
BetaActiveBatteryERCOTLBNL
305.3 MW storage in Smith, TX · In queue since July 2023 · Proposed COD June 2027
305.3 MW
Capacity
1
Components
Battery
2y 8m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
3y 11m
Facilities Study50%
Queue EntryJul 10, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-06-30
Project Details
State
TX
County
Smith
Region
ERCOT
Developer
SMT Tyler LLC
Utility
—
Entity
ERCOT
Point of Interconnection
3104 Shamburger Switch 138kV
Data Source
LBNL
No news available for this project.