Acker BESS
ERCOT-25INR0460BetaActiveBatteryERCOTLBNL + Live
301.04 MW storage in Castro, TX · In queue since June 2023 · Proposed COD April 2028
301.04 MW
Capacity
1
Components
Battery
2y 10m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
4y 10m
Facilities Study50%
Queue EntryJun 7, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-04-17
Project Details
State
TX
County
Castro
Region
ERCOT
Developer
Ogallala BESS LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
23912 Ogallala 345 kV
Data Source
LBNL + Live
No news available for this project.