John Bull BESS
BetaActiveBatteryERCOTLBNL + Live
147.42 MW storage in Nueces, TX · In queue since July 2023 · Proposed COD April 2028
147.42 MW
Capacity
1
Components
Battery
2y 8m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
4y 9m
Facilities Study50%
Queue EntryJul 31, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-04-16
Project Details
State
TX
County
Nueces
Region
ERCOT
Developer
BRP BLUE TOPAZ 13, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
8482 WEIL TRC4A 138kV
Data Source
LBNL + Live
No news available for this project.