Spaniel Farm Solar Project
BetaActiveSolarERCOTLBNL
100.52 MW generation in Ellis, TX · In queue since May 2023 · Proposed COD April 2027
100.52 MW
Capacity
1
Components
Solar
2y 10m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
3y 11m
Facilities Study50%
Queue EntryMay 3, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-04-12
Project Details
State
TX
County
Ellis
Region
ERCOT
Developer
Energiekontor US Texas SP 18 LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 138 kV 2241 Ennis West Switch - 12320 Templeton
Data Source
LBNL