Tres Rios Ranch BESS — Project Summary

Queue ID
ERCOT-25INR0451
Capacity
290 MW
Technology
Battery
Status
active
Location
Upton, TX
Region
ERCOT
Developer
LectricWind LLC
IA Status
Facility Study

Tres Rios Ranch BESS

ERCOT-25INR0451BetaActiveBatteryERCOTLBNL + Live

290 MW storage in Upton, TX · In queue since May 2023 · Proposed COD December 2027

290 MW

Capacity

1

Components

Battery

2y 11m

In Queue

Facility Study

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

4y 7m

Facilities Study50%
Queue EntryMay 26, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-12-31

Project Details

State

TX

County

Upton

Region

ERCOT

Developer

LectricWind LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

76008 Twelvemile 345kV

Data Source

LBNL + Live