Waterloo BESS 1
ERCOT-25INR0447BetaActiveBatteryERCOTLBNL + Live
105.64 MW storage in Bastrop, TX · In queue since May 2023 · Proposed COD December 2027
105.64 MW
Capacity
1
Components
Battery
2y 11m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
4y 7m
Facilities Study50%
Queue EntryMay 15, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-12-01
Project Details
State
TX
County
Bastrop
Region
ERCOT
Developer
Waterloo Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV 7040 AUSTROP - 7048 GARFIELD
Data Source
LBNL + Live
No news available for this project.