Peridot Storage — Project Summary

Queue ID
ERCOT-25INR0444
Capacity
50.48 MW
Technology
Battery
Status
active
Location
Zavala, TX
Region
ERCOT
Developer
BT Castro Storage, LLC
IA Status
Facility Study

Peridot Storage

BetaActiveBatteryERCOTLBNL

50.48 MW storage in Zavala, TX · In queue since May 2023 · Proposed COD December 2025

50.48 MW

Capacity

1

Components

Battery

2y 10m

In Queue

Facility Study

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

2y 7m

Schedule

3 months past proposed COD

Facilities Study50%
Queue EntryMay 26, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-12-31

Project Details

State

TX

County

Zavala

Region

ERCOT

Developer

BT Castro Storage, LLC

Utility

Entity

ERCOT

Point of Interconnection

5836 North Batesville 69kV

Data Source

LBNL