Stephens Ranch Wind Repower
BetaActiveWindERCOTLBNL + Live
12.4 MW generation in Borden, TX · In queue since June 2023 · Proposed COD October 2027
12.4 MW
Capacity
1
Components
Wind
2y 9m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
4y 4m
Facilities Study50%
Queue EntryJun 28, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-10-01
Project Details
State
TX
County
Borden
Region
ERCOT
Developer
Stephens Ranch Wind Energy, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
59900 Long Draw 345 kV
Data Source
LBNL + Live