Brackens BESS — Project Summary

Queue ID
ERCOT-25INR0424
Capacity
103.58 MW
Technology
Battery
Status
active
Location
Freestone, TX
Region
ERCOT
Developer
Brackens BESS
IA Status
Facility Study

Brackens BESS

BetaActiveBatteryERCOTLBNL

103.58 MW storage in Freestone, TX · In queue since May 2023 · Proposed COD August 2026

103.58 MW

Capacity

1

Components

Battery

2y 10m

In Queue

Facility Study

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

3y 3m

Facilities Study50%
Queue EntryMay 3, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-08-07

Project Details

State

TX

County

Freestone

Region

ERCOT

Developer

Brackens BESS

Utility

Entity

ERCOT

Point of Interconnection

3558 Ranchland 138 kV

Data Source

LBNL

No news available for this project.