Brackens Solar
BetaActiveSolarERCOTLBNL
177.24 MW generation in Freestone, TX · In queue since May 2023 · Proposed COD August 2026
177.24 MW
Capacity
1
Components
Solar
2y 10m
In Queue
Facility Study
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
3y 3m
Facilities Study50%
Queue EntryMay 15, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-08-07
Project Details
State
TX
County
Freestone
Region
ERCOT
Developer
Brackens Solar
Utility
—
Entity
ERCOT
Point of Interconnection
3558 Ranchland 138 kV
Data Source
LBNL
No news available for this project.