Aldrin 138 BESS — Project Summary

Queue ID
ERCOT-25INR0421
Capacity
207 MW
Technology
Battery
Status
active
Location
Brazoria, TX
Region
ERCOT
Developer
Aldrin Energy Storage LLC
IA Status
IA Executed

Aldrin 138 BESS

ERCOT-25INR0421BetaActiveBatteryERCOTLBNL + Live

207 MW storage in Brazoria, TX · In queue since May 2023 · Proposed COD July 2027

207 MW

Capacity

1

Components

Battery

2y 11m

In Queue

IA Executed

IA Status

Signed Apr 2024

Interconnection Timeline

Queue → IA

11 months

IA → COD

3y 3m

Total Duration

11 months

Construction75%
Queue EntryMay 15, 2023

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementApr 18, 2024

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 6–18 months

Commercial Operation

Proposed COD: 2027-07-01

Project Details

State

TX

County

Brazoria

Region

ERCOT

Developer

Aldrin Energy Storage LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

(Bus: 39015) North Alvin TNMP 138kV

Data Source

LBNL + Live