Palacios BESS
BetaActiveBatteryERCOTLBNL
125.69 MW storage in Cameron, TX · In queue since May 2023 · Proposed COD November 2027
125.69 MW
Capacity
1
Components
Battery
2y 10m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
4y 6m
Facilities Study50%
Queue EntryMay 15, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-11-28
Project Details
State
TX
County
Cameron
Region
ERCOT
Developer
BRP BLUE TOPAZ 11, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
5767 HIWAY511SUB8 138kV
Data Source
LBNL