WOE Gyp King Wind
BetaActiveWindERCOTLBNL + Live
315 MW generation in King, TX · In queue since April 2023 · Proposed COD August 2030
315 MW
Capacity
1
Components
Wind
2y 11m
In Queue
Facility Study
IA Status
COD target: 2030
Interconnection Timeline
Total Duration
7y 4m
Facilities Study50%
Queue EntryApr 19, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2030-08-31
Project Details
State
TX
County
King
Region
ERCOT
Developer
White Oak Energy, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 138kV 33798 GYP_18 _x0013_ 6088 BENJ4A
Data Source
LBNL + Live
No news available for this project.